BRITISH COL UMBIA UTILITIES COM MISSION ORDER N UMBER G -18-05 SIXTH FLOOR, 900 HOWE STREET, BOX 250 TELEPHONE: (604) 660-4700 VANCOUVER, B.C. V6Z 2N3 CANADA BC TOLL FREE: 1-800-663-1385 web site: http://www.bcuc.com FACSIMILE: (604) 660-1102 IN THE MATTER OF the Utilities Commission Act, R.S.B.C. 1996, Chapter 473 and An Application by Canadian Forest Products Limited for a Retroactive Billing Adjustment from British Columbia Hydro and Power Authority BEFORE: L.F. Kelsey, Commissioner ) L.A. OHara, Commissioner ) February 10, 2005 O R D E R WHEREAS: A. On December 19, 2001, the Commission, by Order No. G-141-01, approved for British Columbia Hydro and Power Authority (“BC Hydro”) its November 23, 2001 Special Electric Service Agreement, Tariff Supplement No. 60 with Canadian Forest Products Ltd. (“Canfor”) Upper Fraser Sawmill for a Bypass Rate at the equivalent of Rate Schedule 1821 plus a monthly rider of $5,777.25 for a period of 20 years effective June 1, 2002; and B. On April 23, 2004, BC Hydro applied to the Commission, with approval from Canfor as a co-signing party to its letter, formally requesting that Tariff Supplement No. 60 be cancelled because Canfors Upper Fraser sawmill had been permanently closed; and C. By Order No. G-45-04 dated May 7, 2004, the Commission approved the cancellation of the Bypass Rate Special Electric Service Agreement (Tariff Supplement No. 60) effective the date of the Commission Order; and D. By letter dated September 14, 2004, Canfor requested Commission approval of a retroactive billing adjustment by BC Hydro, effective August 1, 2003, to remove the impact of the billing demand charges determined using the demand ratchet clause in Rate Schedule 1821; and E. By letter dated September 29, 2004, the Commission requested comment on the Canfor request from BC Hydro; and F. In a letter dated January 28, 2005, BC Hydro responded that it supports Canfors application and suggested that if the Commission approves Canfors request that the approval be made applicable to the August 2003 through May 2004 billing periods; and G. The Commission has reviewed the application and finds that it should be approved. . . . /2
2 NOW THEREFORE the Commission orders as follows: 1. The Commission approves the Canadian Forest Products Limited request that BC Hydro retroactively adjust the bill of Canfors Upper Fraser Sawmill Division to remove the impact of Billing Demand Charges determined using the demand ratchet mechanism in Rate Schedule 1821. 2. The adjustment should apply to the August 2003 to May 2004 billing periods. DATED at the City of Vancouver, in the Province of British Columbia, this 18th day of February 2005. Orders/BCH_Canfor UpFrsr RetroBill Adjust BRITISH COLUMBIA UTILITIES COMMISSION ORDER NUMBER G-18-05 BY ORDER Original signed by: L. F. Kelsey Commissioner
 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.