Orders

Decision Information

Decision Content

                        BRIT ISH  COLU   MBIA         UTIL IT IES  COM   MISSION                     ORDER         NUMBER   G ‐16508                    SIXTH FLOOR900 HOWE STREETBOX 250  TELEPHONE:  (604)  6604700  VANCOUVERB.C.  V6Z 2N3   CANADA  BC TOLL FREE:  18006631385  web sitehttp://www.bcuc.com  FACSIMILE:  (604)  6601102      IN THE MATTER OF  the Utilities Commission ActR.S.B.C1996Chapter 473    and    An Application by FortisBC Inc for a Certificate of Public Convenience and Necessity  for the Copper Conductor Replacement Project      BEFORE AARhodesCommissioner    R.JMilbourneCommissioner    P.EVivianCommissioner    November 72008    O  R  D  E  R  WHEREAS   A On June 272008FortisBC Inc. (“FortisBC”, “the Company”) applied to the British Columbia Utilities  Commission (the “Commission”) for a Certificate of Public Convenience and Necessity (“CPCN”) for the  Copper Conductor Replacement Project (the “Project”) (the “Application”); and    B. The Project consists of replacement of 85 percent of its No8No6 and No90 MCM copper distribution  conductors with aluminum conductor steel reinforced (“ACSR”) conductorsassessment of poles for age and  safety and replacementsubject to the assessment resultupdates to the Geographic Information Systems  Databasestandardization as per FortisBC existing standards for distribution linesand disposal of the  replaced copper conductors through saleand    C. The Project is expected to start in the first quarter of 2009 and be completed by the fourth quarter of 2018 with estimated capital expenditures of approximately $103 millionincluding the cost of removalsover the  tenyear life of the Project.  The net present value (“NPV”) of the Project is estimated at approximately  $59 million with an estimated NPV of Customer Rate Impact at 0.15 percent.  Although the Company is  seeking approval of the Projectit is only seeking expenditure approval out to 2010 of $11.7 million.  The  Company proposes to seek further approval for expenditures beyond 2010 in its future Capital Expenditure  Plansand    D. By Order G10808 the Commission established a Written Public Hearing Process and Regulatory Timetable  and ordered that a Workshop be held in KelownaB.Con August 122008and    . . ./2 
        BRIT ISH  COLUMBIA     UTIL IT IES  COMMISSION               ORDER      NUMBER   G16508        2      E. The Written Public Hearing process concluded with the filing of FortisBCs Reply Submission on  September 292008and    F. The Commission has considered the Application and the evidence and the submissions of the parties     NOW THEREFORE the Commission orders that the FortisBC Application for a CPCN for its Copper Conductor  Replacement Project is denied.  The Commissions determination is set out in the Reasons for Decision attached  as Appendix A to this Order     DATED at the City of Vancouverin the Province of British Columbiathis       7 th        day of November 2008     BY ORDER      Original signed by     A.ARhodes    Commissioner    Attachment    Order/G16508_FortisBC_CPCN Copper ConductorReasons for Decision 
APPENDIX A  to Order NoG16508  Page 1 of 10  FORTISBC INC   APPLICATION FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR THE  COPPER CONDUCTOR REPLACEMENT PROJECT      REASONS FOR DECISION      1.0  THE APPLICATION    By letter dated June 272008 FortisBC Inc. (“FortisBC”) filed an application  to the British Columbia Utilities  Commission (“the Commission”) for a Certificate of Public Convenience and Necessity (“CPCN”) pursuant to  section 45 of the Utilities Commission Act R.S.B.C1996 c473   (“the Act”) to replace certain of its copper  conductors and perform other related work over a ten year period (“the Project”) (“the Application”).    More specificallythe Project would entail   replacement of 85 percent of all No8No6 and No90 MCM Copper Distribution Conductors with  Aluminum Conductor Steel Reinforced (ACSRConductor;      assessment of poles for age and safety and replacement subject to the assessment result   updates to the Geographic Information Systems (“GIS”) Database   standardization as per FortisBC existing standards for distribution linesand    disposal of the replaced copper conductors through sale     (Exhibit B1pp726   In the ApplicationFortisBC seeks approval for the ten year Project generallybut has only provided cost  estimates for the first two years totalling $11.7 million with a +/‐ 20 percent level of certainty.  FortisBC  anticipates the total cost of the Project to be approximately $103 million but takes the position that it cannot  determine the level of accuracy of the cost estimates for the future years with any certainty due to the length of  the Project and the volatility of costs in the utility industry.  It proposes to seek further approval for future  expenditures in its Capital Expenditure Plans. (Exhibit B1p7 Updated   FortisBC states that the Project is necessary to ensure a “safe and reliable distribution system.”  (Exhibit B1 p7    
APPENDIX A  to Order NoG16508  Page 2 of 10      2.0  THE PROCESS    Upon receipt of the Applicationthe Commission issued Order G10808 which established a written hearing  procedure and regulatory timetable.     A Workshop presentation was held in KelownaB.Con August 122008   There were two rounds of Information Requests (“IRs”) from the Commission and one round of IRs from the  Intervenors.  Only the B.COld Age Pensioners’ Organization etal. (“BCOAPO”) participated in the Intervenor  IRs.  Buryl SlackGoodman and Hans Karow also registered as Intervenors and provided comments FortisBC filed its Final Submission on September 162008.  The BCOAPO filed its Final Submission on  September 222008 and FortisBC replied on September 292008.       3.0  POSITIONS OF THE PARTIES    No Intervenors opposed the Project   The BCOAPO appears to support the Project but recommends that FortisBC be required to file annual reports  concerning the Project.  According to BCOAPOsuch filings will allow stakeholders to consider the Companys  experience and spending to date when the spending requests for the Project are reviewed as part of future  Capital Expenditure Plans     4.0  THE PROJECT    (i) Existing System    FortisBC is an investorowned,  integrated utility engaged in the business of generationtransmission distribution and sale of electricity in the southern interior of British Columbia.  FortisBC owns assets of  approximately $850 millionincluding four hydroelectric generating plants and approximately 6,850 circuit  kilometres of transmission and distribution power lines.  (Exhibit B1p8)  FortisBC states that it “has  approximately 4,900 circuit kilometres of overhead distribution lines in its systemconsisting of approximately  9,300 kilometres of conductor.  Of thisapproximately 660 circuit kilometres or 13.5 percentis made up of  copper conductors ranging in size from No8 to 300 MCM.  Approximately 500 circuit kilometres of the copper  distribution lines or 960 kilometres of conductor is ... [made upof No8No6 and 90 MCM (legacycopper  which is supported by approximately 8,100 poles.”  (Exhibit B1p10)  The term “legacy copper” refers to all  FortisBCs No8No6 and No90 MCM copper conductor.  (Exhibit B4,  BCOAPO I.R.1.2.1)     FortisBC notes that the legacy copper was commonly used for distribution lines 50 years ago due to its “excellent  electrical characteristics” and availabilitybut that the metallurgical characteristics have deteriorated with the  passage of time.  A majority of the poles which support the legacy copper were installed at the same time as the  legacy copper conductor such that approximately 4,450 poles are now over 50 years old.  (Exhibit B1p10    
APPENDIX A  to Order NoG16508  Page 3 of 10      Table 1 shows the Legacy Copper Conductor Type and Age Profile     (Exhibit B1p.11     The table below shows the approximate age of legacy versus nonlegacy conductors in the FortisBC system     (Exhibit B4BCUC I.R2.35.1     (ii) Copper Conductor Failure    FortisBC reports that over the past five yearssome 200 out of a total of 350 conductor failure incidentsor 57  percentinvolved legacy copper conductor which only makes up roughly 10 percent of the total conductor in  service.  (Exhibit B1p13    
APPENDIX A  to Order NoG16508  Page 4 of 10      FortisBC further states that “within the last four yearstwelve incidents involving copper conductor resulted in  situations where downed conductors remained energizedcreating a public and employee electrocution risk and  a fire hazard.”  (Exhibit B1p13)  Howeverno injuries in fact resulted.  (Exhibit B4BCUC I.R2.34.1).     FortisBC details these twelve incidentsnoting that four of the twelveor one thirdinvolved No.’s 3 and 4  copper conductors which are not attributable to the conductor itselfbut to the Hot Tap Connectors which are  directly applied to the conductor without the use of Stirrups.  The replacement of the No.’s 3 and 4 conductors  will be kept outside the scope of the Project. (Exhibit B1p15Table 3   FortisBC notes a particular concern for conductor failure in “Sensitive Areas” which it considers to include school  zonespublic parksand high density residential and commercial areas.  It has identified 187 locations in  Sensitive Areas where No8No6or No90 MCM copper are present as follows       (Exhibit B1pp1516     To dateupgrades of legacy copper conductor have primarily been undertaken when the conductor failed.   FortisBC is now concerned that the global issue of the deterioration of the legacy copper is not resolvedFortis  BC notes that “[p]ast experience and laboratory analysis has shown that deterioration has compromised the  integrity of these conductors and they pose a risk not only to the line crews who work on thembut also to the  general public”.  (Exhibit B1p16) (emphasis added   FortisBC provides a summary of the independent laboratory analysis (Exhibit B1Appendix Awhich includes the  following points   annealing (softeningof the copper conductor can lead to ductile overload failure under normal  operating stress annealing is occurring due to elevated service temperatures from high contact resistance within  connections the increase in contact resistance is from the large scale build up of corrosion product within the  connection  
APPENDIX A  to Order NoG16508  Page 5 of 10      similar conditions are likely to exist in the majority of the hot tap connections and additional failures can  be expected additional splice connections showed evidence of annealingand  conductor material properties outside of connection areas were below todays specified requirements  for copper conductor wireresulting either from long service life or less stringent standards at the time  of installation (Exhibit B1pp2122   (iii) Poles    FortisBC notes that the structural integrity of wood poles also decreases with age.  It estimates the maximum  expected service life of its poles to range between 50 and 70 years.  (Exhibit B1pp2223)      FortisBC reports that it has some 82,000 wood poles in  servicethat those greater than 15 years of age are  tested on an eight year cycleand that on averagetwo percent need to be replaced for an average annual  replacement rate of 130/year. (Exhibit B2BCUC I.R1.14.4   There are 8,100 poles supporting the legacy conductor.   FortisBC proposes to replace 3,900 of the 4,450 poles  which are 50 years of age or older and support the legacy copper as part of the Projectto avoid duplication of  effort in the future.  The remaining legacy poles are expected to be replaced in the ordinary course through  other projects over the next ten years. (These numbers may change somewhat following destructive testing and  analysis of a sample of the poles which are replaced in the early years of the Project to determine the existence  and possible length of any residual life.) (Exhibit B1pp2427   (iv) Options considered    FortisBC notes that the alternatives of “Do nothing” or “Run to Failure” are not viable options due to the safety  concerns. (Exhibit B1p26   (v) Implementation     The preferred implementation plan for the first three years of the Project involves the replacement of legacy  copper conductors and poles in sensitive areas as follows     Year 1  (2009   All legacy copper conductors near school zones will be replaced as will No8 copper conductors in the vicinity of  parks  
APPENDIX A  to Order NoG16508  Page 6 of 10        This will result in the replacement of approximately 22 circuit kilometres of conductorthe reconductoring of 36  locations and the replacement of approximately 200 poles     Year 2  (2010   All remaining No6 and 90 MCM copper conductors in the vicinity of parks will replaced as will No8 copper  conductors in the vicinity of high density residential areas   This will result in the replacement of approximately 29 circuit kilometres of conductorthe reconductoring of 41  locations and the replacement of approximately 260 poles     Year 3  (2011   All remaining No6 and No90 MCM copper conductors in the vicinity of high density residential and high  density commercial areas will be replaced   This will result in the replacement of approximately 66 circuit kilometres of conductorthe reconductoring of  110 locations and the replacement of approximately 590 poles.     In the final resultover the first three years of the Project18 percent of the No90 MCM34 percent of the No 8 and 26 percent of the No6 copper conductor in the FortisBC service area will be replaced along with 1,050  legacy poles.  This will result in the elimination of copper conductor in all 187 locations identified as Sensitive  Areas.  (Exhibit B1pp2829     Other implementation plans were investigated which involved the same work being donebut over longer time  periods.  These plans were rejected due to the higher level of safely risk from the extended time to completion  of the work and somewhat higher rate impacts.  (Exhibit B1pp5657   The comparative economic impacts of the three implementation scenarios are set out in the table below:       
APPENDIX A  to Order NoG16508  Page 7 of 10        (Exhibit B1p58 Updated     5.0  PROJECT COSTS    As noted aboveFortisBC has provided cost estimates for the first two years of the Project onlywith a level of  accuracy of +/‐ 20 percent.  The cost estimate is based on an average cost per kilometre multiplied by the length  of the distribution line to be replaced.  The total Project cost estimate of $103 Million is characterized as an  order of magnitude value   Assumptions underlying the cost estimate include the work being performed in snowfree conditionsreuse of  existing circuit alignments where possible and outages with standby generation for extended outages or critical  uses only.  It is further assumed that the structures will be replaced with single pole structures with “a typical  ruling span of 70 meters”, that 65 percent of the old circuits will require pole replacements and full rebuilding including anchoringand that 70 percent of structures are tangents with the remaining 30 percent being either  angles or deadends.  (Exhibit B1p48 Updated   The two year cost estimate for the Project is set out in further detail in the table below    
APPENDIX A  to Order NoG16508  Page 8 of 10          (Exhibit B1p49     6.0  PROJECT BENEFITS    The Project is being advanced on the basis of improved safety.  Additional benefits are stated to include:  likely  improved customer reliability (from reduced failures of conductors), reduced electrical line losses (due to the  reduced line resistance and increased current carrying capacity of new conductor), reduction in unexpected  failures (with their corresponding “urgent” capital replacement costsand reduction in the cost of ongoing  Distribution Line Rebuilds” as some of the work is shifted to the Project.  (Exhibit B1pp3945     7.0  RATE IMPACT    Section 4 above reproduces Table 10 from the Application to illustrate the comparative economic impacts of the  three implementation scenarios for the Project.  Table 10 also shows the Net Present Value of the Rate Impact of  the three scenarios.  The Net Present Value of Rate Impact of the preferred alternative is estimated to be 0.15  percent with a maximum one time Rate Impact of 0.56 percent      
APPENDIX A  to Order NoG16508  Page 9 of 10      8.0  COMMISSION DETERMINATION    The Commission Panel has considered the evidence and the submissions in light of the governments energy  objectives and agrees with FortisBC that the primary rationale for the proposed Project is the safety of FortisBC  personnel and the public it servesThe projected ancillary benefitswhile in some cases tangibleareall else  equalunlikely to be sufficient to support a determination that the Project could be in the public interest   The Commission Panel also notes FortisBCs reliance on the results of the independent laboratory analysis to  establish that the replacement of the legacy copper conductor will mitigate the disproportionate occurrence of  failure statistically associated with the legacy copper conductors visàvis the other conductors used in its  system   Accordinglythe Commission Panel has carefully reviewed the PowerTech Report provided as Appendix A to the  Application and notes that   of the 12 conductor samples submitted for analysissix were of legacy copper conductorand six were of  Nos 23 and 4 nonlegacy copper conductorwhich are excluded from the scope of the Project the nonlegacy samples included one with a failed hot tap connectionand two with unfailed line  splicesthe balance were connectionfree conductor wire samplesas were all of the legacy samples  submitted (p.7 Table 2) .  metallographic examination of the failed hot tap sample from nonlegacy conductor confirmed the root  cause of failure as annealing due to local resistance heatingsimilar examination of the unfailed splice  samples from nonlegacy conductor confirmed similar annealing local to the splices physical testing of the nonlegacy samples containing connections confirmed that three inches distant  from the connectionthe properties of the conductor itself were unaffected (pp 361213).  physical testing and metallographic examination of both the connectionfree legacy and nonlegacy  conductor samples confirmed that the material properties are slightly below that of the nominal values  dictated by the current standard (p.13) (emphasis added).      In the absence of any evidence as to the nature and cause of the failures in the legacy copper systemand given  the expert opinion that the properties of  both legacy and nonlegacy conductor material are unaffected outside  of any connection areasand that those properties are only slightly  below todays standardthe Commission  Panel is unable to share FortisBCs conclusion that replacement of all of the legacy copper conductor will  mitigate the disproportionate occurrence of failure statistically associated with the legacy system.     The Commission Panel is further concerned that the accelerated replacement of the legacy copper system as  proposed in the Project would also result in the rate of pole replacement across the whole Fortis BC system  being materiallyand potentially unnecessarilyincreased from its current level of 130/year by some or all of the  390 legacy system poles/year proposed to be replaced on average over the ten year life of the Project   For these reasonsthe Commission Panel cannot conclude that the expense associated with the Project as  submitted is justifiedand accordingly denies the Application  
APPENDIX A  to Order NoG16508  Page 10 of 10        Howeverthe Commission Panel accepts that the options of “do nothing” or “run to failure” are not viable where  there are safety concernsIfin factFortisBC has knowledge of specific conditions in its legacy copper system  where factors such as hot tapssplicesor other circumstances are playing a role in triggering failures in its legacy  copper systemthengiven its obligation to mitigate risks to the safety of its workforce and the publicthe  Commission Panel believes that Fortis BC should be addressing these on a priority basis in the normal course of  the operations and maintenance of its system   The Commission Panel further observes that FortisBC has the option to deal with the balance of its concerns as  to the integrity of its legacy copper system over the course of the next ten to fifteen years under its normal  Capital Growth and Sustaining programsas it proposes to do for its nonlegacy copper system. (Exhibit B1 p27    
 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.