Orders

Decision Information

Decision Content

                    ERICA MHAMILTON  COMMISSION SECRETARY  Commission.Secretary@bcuc.com  web sitehttp://www.bcuc.com          VIA EMAIL  wjandrews@shaw.ca    MrWilliam JAndrews  Barrister & Solicitor  1958 Parkside Lane  North VancouverBC  V7G 1X5      Dear MessrsAndrewsHorne and Cairns   Re:  FortisBC Inc. (“FortisBC”)  Ellison Substation Project 3698442  Applications for Reconsideration of Commission Orders C0407 and G7507    This letter is in response to the letters of September 182008 (Concerned Citizens of Quail Ridge and Lochrem  Road “CCQRLR”) and September 232008 (Quail Ridge Residents Association “QRRA””) in which the respective  organizations sought a reconsideration of the Commissions Decision approving the FortisBC Application of  October 272006 for a Certificate of Public Convenience and Necessity (“CPCN”) for the Ellison Substation at the  Lochrem Road site.  The relevant Commission Orders that set out the details of the approval are C407 and  G7507 Background  The history of the proceedings leading to this reconsideration is set out in the recitals of Order G16608 and will  not be repeated here The Commission granted a reconsideration but limited the scope of the written process that was to follow.   Commission Order G16608 dated November 182008 sets out the issues that the Commission found were  worthy of further examination.  The Order provided (in part):            LETTER NOL809        SIXTH FLOOR900 HOWE STREETBOX 250  VANCOUVERB.C.  CANADA  V6Z 2N3  TELEPHONE:  (604)  6604700  BC TOLL FREE:  18006631385  FACSIMILE:  (604)  6601102      Log No27301  February 32009    kac@caurbskaw.ca    MrKelly ACairns  Cairns Law Corporation  Suite 207 – 1664 Richter Street  KelownaBC  V1Y 8N3    budley1@shaw.ca    RHorne  President  Concerned Citizens of Quail Ridge and Lochrem Road     
    2      1 The Commission establishes a written hearing to reconsider the Decisionso as to address the  initial question of whether the Ellison Substationas proposed and approved at the Lochrem  Road sitewill cause problems for the systems at the Kelowna Airport under the terms specified  the NAV CANADA Agreements andif problems are causedthe changes that will be needed to  remedy the situationand the cost of the changes (the “Initial Issue”).    2 By MondayDecember 12008FortisBC will file an independent engineering Report (the  Report”) by a properly qualified individual or group that reviews the siting and design of the  Ellison Substation as proposed and approvedrelative to the requirements of NAV CANADA as  set out in the Agreementsand which confirms that the substation will comply with the  requirements.  If this confirmation cannot be providedthe Report will describe the changes to  the substation that are needed to bring it into complianceand the estimated cost of these  changes   3 FortisBC will provide a copy of the Report to Intervenors and Interested Parties in the Ellison  Substation CPCN proceedingparties who participated in the reconsideration phase one  comment process and NAV CANADA (collectively the “Participants”).    In briefthe Commission was concerned that the matter of possible radio interference with the landing and  communication systems at the Kelowna Airport had not been brought to the attention of the Commission Panel  considering the CPCN application and as it appearswas not investigated by FortisBC in any detail until after the  CPCN had been granted.  The Commission notes (as have the Parties and interested personsthat the Transport  Canada document TP 1247 Part IIadvises that   Consultation… must take place at an early stage in the project in order to avoid costly  redesign or undue pressure when seeking building and site approvals.  It is recommended  that consultation take place at the building concept stagebefore site approval is sought.”    Had FortisBC followed this recommendation and presented the issues associated with radio interference in the  original CPCN Applicationthe Commission Panel dealing with the CPCN application would have had the relevant  information before iton the recordand could have afforded the matter the attention it deserved thenand  precluded much of the timeeffortexpense and delay that has now come to pass   The Lochrem site for the Ellison Substation is located closer than 3.2 kilometers from the centre line of a runway  of the Kelowna Airport and may therefore cause electromagnetic interference (“EMI”) to aircraft landing  systems operated by NAV CANADA.  FortisBC and NAV CANADA entered into an Operating Agreement and a  Statement of Work Agreement dated October 82008 (the “Agreements”).  The Agreements oblige FortisBC to  monitor the level of EMI levels at the Ellison Substation and to correct the cause if the EMI level exceeds a  specified level (Exhibit C52).    After reviewing the submissions in the first phase of the reconsideration processthe Commission was unclear as  to the materiality of the risk that the Agreements may require FortisBC to make significant changes to the  substationor perhaps relocate it.  The additional cost of such changes could impact ratepayersand  consequently the Commission granted a reconsideration on its merits of the “Initial Issue”.    This Reconsideration has been considered by a Panel of four Commissioners who have reviewed the record of  this Reconsideration and the positions advanced by FortisBCthe CCQRLRQRRA and the other interested parties  that provided submissions and argument
    3      The Independent Engineering Report (the “Report”)    In accordance with Order G16608Fortis filed the Report authored by PDK Airport Planning Incand CNSS  Engineering Services.  The Report was filed as Exhibit C53 on December 12008.  The Commission Panel has  relied upon the professional opinions put forth in the Report and is of the view that the Report meets the  requirements set out in the above Order   Howeverthe Commission Panel does find that the Report would have been more helpful if the authors had  canvassed the possible mitigation measures that might be required in more detailand provided greater  specificity as to the range of costs that might be expected.  It is understood that no firm pricing estimates could  have been given for unknown problem areas or their respective fixes.     The Commission Panel is of the view that the Reportwhile measured in its languagedoes provide a balanced  and thorough analysis of the technical matters at issue and which could give rise to EMI.      The concluding remarks of the Report state   a The NavCanada and SHELBAR tests at a representative substation site showed  negligible amounts of electromagnetic interference being radiated from various  components involved in the operation of the substation.  As long as all equipment and  components in the design of the substation comply with all Industry Canada  equipment interference standards and all electrical work is performed to applicable  Federal Government and Provincial Electrical CodesIndustry standard substation  design will meet NavCanada requirements   b) With regard to the proposed Ellison substation sitein order to meet NavCanadas  requirements for air navigation at the Kelowna Airporta monitoring system was  identified as a mitigating measure.  This measure was requested to insure  electromagnetic noise levels at the site do not interfere with airport communication  and navigational systems.  NavCanada is the owner operator of the Air Navigation  System and has approved the site on that basis   c Although detailed analysis and field tests were completed prior to NavCanada  developing its mitigating measures for substations located in close proximity to an  airportno amount of analysis can predict previously unknown situations.  Corporate  agreements usually contain contract clauses for managing “unspecified perils.”  It is  our opinion that the NavCanada clause requesting a complete shutdown or relocation  of the substation intends to cover off any “unspecified perils” in the event such things  occur.  Should the unthinkable occurother options such as a redesign of the  offending component/circuitrelocation of troublesome circuitsand other similar  measures would be taken before a total relocation of the substation is even  considered   d The proposed Ellison Substation does not violate the Obstacle Limitation Surfaces  identified for the Kelowna Airport.  With respect to any physicalstructural or other  geometric elements of the stationas long as these do not penetrate the Obstacle  Limitation Surfaces at the airportthey should have no effect on the NavCanada  communications or navigational systems.” 
    4      The Final Statement of the Report is   In conclusionbased on our review of the proposed Ellison Substation locationutility  construction methods and maintenance practicesand considering our experience and field  testing at other inservice substationsit is our expert opinion that the Ellison substation  should not cause any problematic interference with the Kelowna Airport Operations.  And  even if some interference were to resultappropriate contingency measures have been  identified and FortisBC has committed to implement these measures to mitigate such  interference.”    The authors do not state that there will be “no interference” at all.  And no guarantees are proffered that the  Ellison substationwhen builtwill meet all of the requirements or guidelines of NAV CANADA.  The Commission  Panel acknowledges this level of assurance would be impossible for any professional to provideat any event  before the substation was built   Other Similar Sites Considered    The Commission Panel takes note of the comparisons that were made with other substations located close to  airports including the following   The SHELBAR study and analysis of the Blackmud substation in NiskuAlbertaand  BC Hydros Kidd substation near Vancouver International Airport   While it is difficult to make any firm decisions for a substation yet to be builton the basis of past experiencethe  Commission Panel found it reassuring that other substations had been sited close to airports without any  reported difficulties.  In the Reportthe authors state in respect of the Kidd substation (that operates at a higher  voltage than will the Ellison substation), “To our knowledgethis facility has not produced any interference  issues with the airports ILS [“Instrument Landing System”]” (Exhibit C53p10).    Further on in the Reportthey state: “We have not heard of any substations being required to mitigate  electromagnetic noise levels after it was in service.”  And “We are not aware of any substations being shutdown  or relocated on account of excessive electromagnetic noise.” (Exhibit C53p10   The Commission Panel concludes that there is no evidence that electromagnetic noise (“EMN”) levels generated  by substations located near or in proximity to airports or the associated flight paths poses any likely or recurring  problem.  Indeedwhile there are mitigating and remedial steps that could be taken if such interference was  experiencedthere is nothing on the record to show that such steps have been necessary.     The Kelowna Topography and its Effect on EMN    The impact of the surrounding topography on EMN was raised by MsFortunat (Exhibit C42).  This concern is  addressed within the Report which states that where there are mountains near a site there is a potential for  secondary reflection referred to as “multipath” reflection.  The Report goes on to outline the complex nature of  such phenomena and their dependence on a variety of local factors such as obstruction size and distance from  the site.  The Report concludes that “it is very unlikely surrounding topography could elevate electromagnetic  noise levels above those expected from a normal operation at the site” (Exhibit C53).   
    5      The Commission Panel finds that the topography in the vicinity of the Lochrem site is not expected to increase  the EMI impact on the systems at the airport   Proper EquipmentInstallationand Maintenance    The Commission Panel is of the view that the key to minimizing EMI from any electrical apparatus is a  combination of component and system design (standards and codesand good maintenance practices.  Perhaps  of thesegood maintenance procedures are the most important (Exhibit C53p9Question 4).  The Ellison  Substation will be built to normal standards and codes as prescribed by the various government and industry  authorities and the monitoring system as outlined in the Agreements signed with NAV CANADA will provide early  warning of any deterioration in system components.  The three levels of warning in the Operating Agreement and the computerized recording and storage of the levels data by NAV CANADA will provide a database that will  assist in carrying out timely maintenance as required and if deficiencies are notednew maintenance routines  can be developed   Mitigating and Remedial Measures    The Commission Panel accepts as a fact that there will be some level of EMN generated at this (and allhigh  voltage substations.  The issue is one of degree and corrective or remedial measures.  The EMN levels set out in  the Operating Agreement are extremely low and even if exceededmay not cause operational difficulties for the  ILS receivers.  In any eventthe reporting and remedial measures that are set out in the Operating Agreement  appear to the Commission Panel as sufficient to meet most of the definable and expected problems that may  arise in the course of operating the substation.  There are provisions for noticenegotiation and resolution of  any problems.  Arbitration is available in the face of deadlock or lack of agreement.  There appear to be many  measures that can be employed to reduce EMN such as those set out in subsection (cof the Concluding  Remarks of the Report.     Commission Panel Determination    The Commission Panel accepts the position of QRRA and CCQRLR that the Report does not conclusively confirm  that the Ellison Substation will comply with the requirements of NAV CANADA as set out in the Agreements.   Thereforethere is some risk that FortisBC may need to make certain expenditures to meet these requirements.   At a minimumFortisBC estimates that the monitoring equipment will cost $135,000 and that extra operating  and maintenance costs will be $6,250 per year (Exhibit C55Horne IR 9).  Howeverthese additional costs are  not sufficient to raise doubts whether the Lochrem Road site is appropriate   The issue for deciding whether or not to proceed with a full reconsideration of the project as approved at the  Lochrem siteis whether there is a material risk that FortisBC will be required to make additional significant  expenditures to meet its obligations under the Agreements   Having reviewed all the submissions of the Parties and the findings in the Reportthe Commission Panel finds  that the Ellison Substationas proposed and approved at the Lochrem Road siteis very unlikely in the extreme to cause any problems for the systems at the Kelowna Airport.  Furtherthe Commission Panel is convinced that  the monitoring system and the remedial measures anticipated in the Operating Agreement between FortisBC  and NAV CANADA will be sufficient to provide advanced warning of any problem EMN and to provide a context  for resolution of any such problem once identified.      
    6      In the absence of persuasive evidence that FortisBC will be unable to meet its obligations under the Agreements  or that FortisBC is at significant risk of having to make material additional expenditures to comply with the  Agreementsa full reconsideration of the Commissions decision to grant a CPCN for the Ellison Substation at the  Lochrem site is not warranted   Thereforethe Commission Panel denies the applications of CCQRLR and QRRA for a further expanded  reconsiderationand reaffirms the approval for the Ellison Substation as set out in Orders C407 and G7507     Yours truly     Original signed by     Erica MHamilton    ac  cc MrDavid Bennett    Vice PresidentRegulatory Affairs & General Counsel    Regulatory Affairs Department    FortisBC Inc   1290 Esplanade    PO Box 130    TrailBC   V1R 4L4    (Via email:  david.bennett@fortisbc.comregulatory@fortisbc.com     Interested Parties (FBCEllisonCPCNIP   PF/FortisBC_Ellison Reconsideration/L809  Reasons for Decision 
 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.