                              BRIT I SH  COLUMBIA     UTIL I T I ES  COMMISS ION                   ORDER       NUMBER   G17009            SIXTH FLOOR900 HOWE STREETBOX 250  TELEPHONE:  (604)  6604700  VANCOUVERB.C.  V6Z 2N3   CANADA  BC TOLL FREE:  18006631385  web sitehttp://www.bcuc.com  FACSIMILE:  (604)  6601102    IN THE MATTER OF  the Utilities Commission ActR.S.B.C1996Chapter 473    and    An Application by Shaw Cablesystems Limited and Shaw Business Solutions Inc to continue to use FortisBC Inc.’s Transmission Facilities      BEFORE AARhodesCommissioner    MRHarleCommissioner  December 232009    LAOHaraCommissioner    O R D E R    WHEREAS   A On October 262009 Shaw Cablesystems Limited and Shaw Business Solutions Inc. (collectively “Shaw”) applied for an  order directing FortisBC Inc. (“FortisBC”) to allow Shaw to continue to use FortisBCs electric transmission facilities for  Shaws telecommunication facilities throughout the FortisBC service area pursuant to section 70 of the Utilities  Commission Act (the “Application”); and    B. The Application requests that the British Columbia Utilities Commission (the “Commission”) issue an Order directing  FortisBC to allow Shaw to installoperate and maintain telecommunications cables and related interconnection  facilities on FortisBCs electric transmission facilities including the facilities located on FortisBCs 11 line40 line50 line  and 76 line and setting reasonable terms and rates for Shaws use of FortisBCs facilities.  Shaw submits that such an  order is in the public interestand    C. Shaw has accessed FortisBCs transmission and distribution poles for the placement of telecommunication facilities  since 1972 with the agreement and cooperation of FortisBC and its predecessorsand    D. Shaw submits that the issues in the Application are narrow and centre on fair and reasonable terms and rates and asks  that a Negotiated Settlement Process be set as soon as possibleand    E. On February 132009FortisBC notified Shaw that the Transmission License Agreement will terminate effective  February 122019and     F. On April 32009FortisBC notified Shaw to remove its facilities from FortisBC poles along lines 50 and 54 by April 3 2010 and from poles along lines 40 and 76 by October 312010 in accordance with good utility practice and the  decommissioning of line 40and        …/2 
          BRIT I SH  COLUMBIA     UTIL IT I ES  COMMISS ION               ORDER       NUMBER   G17009  2        G. Shaw disputes the validity of the April 32009 notices and submits they are related to unresolved issues on other  mattersprincipally the ownership of the Kettle Valley telecommunication facilities and FortisBCs dissatisfaction with  the Transmission License Agreement rates and FortisBCs proposal to increase the annual fee from approximately  $40,000 to $927,000and    H. Shaw states that FortisBC recently filed a court action in the British Columbia Supreme Court (the “Court”) that seeks   1) a declaration that the Transmission License Agreement has been terminated 2) a mandatory injunction to have Shaw remove its telecommunications facilities from FortisBCs  transmission facilities and land,   3) an injunction to restrain Shaw from using its telecommunications facilities on FortisBC transmission  facilitiesand    I. By Order G13309the Commission required that FortisBC provide a submission by November 202009 on whether  the Application should be reviewed through a Negotiated Settlement or some other process before the Commission  and for Shaw to make a reply submission by November 272009 on the FortisBC submissionand    J. In its November 202009 submission FortisBC states that it declines to participate in a Negotiated Settlement Process  without having first resolved (by consensual agreement or court determinationthe respective rights of the parties at  issue in the lawsuit because FortisBC considers that concurrent proceedings would not best serve the interests of  ratepayers.  FortisBC states that Shaw accepted the Courts jurisdiction with respect to the dispute and filed a  Statement of Defence.  FortisBC also states that Shaw has advanced its own lawsuit for relief against FortisBC in the  form of a Counterclaimand    K. In its November 272009 Reply submission Shaw notes that FortisBC does not dispute the Commissions authority to  make such an order.  Shaw submits that the public interest calls for the Commission to exercise its authority now.   Shaw also submits that FortisBCs efforts to deny access to its transmission facilities poses an immediate threat to  Shaws communications network and service to its customers.  Shaw argues that failure to agree on the use of a public  utilitys electric transmission facilities is one of the triggers under section 70 for the Commission to interveneand    L. The Commission has reviewed the Application and the submissions and considers that a Preliminary Procedural  Conference is required     NOW THEREFORE the Commission orders as follows   1. A Procedural Conference regarding the review of the Application will be held commencing at 9:30 a.mon January 6 2010 in the Commission Hearing Room on the 12 th  Floor of 1125 Howe StreetVancouverBritish Columbia to address  procedural matters   After the Procedural Conferencethe Commission may either issue a further procedural order and regulatory agenda  for the review of the Application or issue an order declining to review the Application    2. The Commission requires that Shaw and FortisBC be prepared to addressat the Procedural Conferencethe List of  Issues attached as Appendix A to this Order.   …/3 
                  3  3. Shaw and FortisBC are to circulate their respective proposed regulatory timetablesin the event that the Commission  determinesfollowing its consideration of the submissions it receives at the Procedural Conferencethat it should  conduct a review of the Applicationto each other and the Commission by January 42010   DATED at the City of Vancouverin the Province of British Columbiathis          23                 Attachment    Orders/G17009_Shaw Continued Use FortisBC FacilitiesProcedural Conf   BRIT I SH  COLUMBIA   UTIL IT I ES  COMMISS ION         ORDER     NUMBER   G17009          rd          day of December 2009 BY ORDER  Original signed by AARhodes  Panel Chair 
APPENDIX A  to Order G17009  Page 1 of 1    An Application by Shaw Cablesystems Limited and Shaw Business Solutions Inc to continue to use FortisBC Inc.’s Transmission Facilities    LIST OF ISSUES      1. What is the current status of the Shaw and FortisBC Supreme Court proceeding 2. As part of the relief sought in the Supreme Court proceedingsboth Shaw and Fortis seek injunctive relief of an  interiminterlocutory and permanent nature.  In view of its claim of urgencywhy has Shaw not advanced an  application for an interim or an interlocutory injunction 3. Since FortisBC has asked the Supreme Court for a declaration that the Transmission Licence Agreement has  been validly terminated ,  should any section 70 review be limited to 11 line40 line50 line54 line and 76  line and not extend to other transmission lines until the Supreme Court has decided the issue 4. Do Shaw and FortisBC agree that the validity of the termination of the Transmission Licence Agreement is a  matter for the Supreme Courtand not the Commission to decide 5. Why does Section 2.1 of the Application not mention line 54?  Why does Section 2.1 of the Application include  11 line when that line is not identified in the April 32009 FortisBC notices 6. Does Shaw intend to file any further evidence which might assist the Commission in determining the terms  and conditions of Shaws use of the FortisBC facilitiesincluding the terms and conditions respecting the rates  payable for the use?  If sowhen does it intend to do so 7. Shaw states on page 2 of the Application that its requested order is in the public interest.  Does Shaw  therefore accept that a public notice is required 8. What is the appropriate review processwrittenoral or negotiated settlement or a combination of them recognizing that the Negotiated Settlement Process GuidelinesSection 2page 3 states that “Interested  parties cannot be forced to participate in a settlement process”?     9. FortisBC submitted on page 4item 20 of its November 202009 submission that “FortisBC respectfully  submits that the Commission should decline to proceed with Shaws Application.”  Shaws reply of November  272009 on page 4item 2(b), paragraph 2states that “In stark termsFortisBC seeks to terminate whatever  access for Shaw it may have agreed to historically.  Shaws application deals with future access.”  Do FortisBC  and Shaw accept that the Commission can proceed with a review of the Shaw Application concurrent with the  Supreme Court proceeding 10. Other issues identified by the parties 11. Potential Regulatory timetable 12. Location of Hearing  
 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.