Decision Content

                              BRIT I SH  COLUMBIA     UTIL IT I ES  COMMISS ION                   ORDER       NUMBER   G16609            SIXTH FLOOR900 HOWE STREETBOX 250  TELEPHONE:  (604)  6604700  VANCOUVERB.C.  V6Z 2N3   CANADA  BC TOLL FREE:  18006631385  web sitehttp://www.bcuc.com  FACSIMILE:  (604)  6601102    IN THE MATTER OF  the Utilities Commission ActR.S.B.C1996Chapter 473    and    An Application by FortisBC Inc for Approval of a 2009 Rate Design and Cost of Service Analysis        BEFORE A.JPullmanPanel Chair & Commissioner    L.AOHaraCommissioner    M.RHarleCommissioner  December 212009    O  R  D  E  R    WHEREAS   A. On October 302009FortisBC Inc. (“FortisBC”) filed its 2009 Rate Design and Cost of Service Analysis model  with the British Columbia Utilities Commission (the “Commission”), pursuant to sections 58 and 61 of the  Utilities Commission Act (the “Application”).  The Application includes a Rate Design and an accompanying  Cost of Service Analysis (“COSA”), for which FortisBC seeks Commission approvaland    B. By letter to the Commissiondated November 62009BC Municipal Electric Utilities (“BCMEU”) advised the  Commission that it opposes the COSA and Rate Design proposed by FortisBCand states that a Negotiated  Settlement Process is not the appropriate means of addressing COSA principles and rate rebalancing.   BCMEU proposed an oral public hearing as the appropriate forum for the reviewand    C. On November 262009the Commission issued Order G13909establishingamong other thingsa  Procedural Conference to take place in the City of Kelowna on December 152009 and a Preliminary  Regulatory Timetable for the Application which was attached as Appendix “A” to the Orderand     D. The Procedural Conference took place on December 152009.  At the Procedural ConferenceCommission  Staff and FortisBC presented alternative Regulatory Timetables for consideration by the Commission Panel.   The Parties present at the Procedural Conference were invited to make submissions onamong other  mattersthe two alternativesand    E. The Commission Panel has considered the submissions made by the Parties at the Procedural Conference.        
                  2    NOW THEREFORE the Commissionfor the reasons set out in the Reasons for Decision attached as Appendix “A”  to this Orderorders as follows   1. The Application is to proceed by way of an Oral Public Hearing commencing MondayMay 32010 at  9:00 a.min the City of Kelownaat a location to be determined by a further Order   2. The Preliminary Regulatory Timetable attached as Appendix “A” to Order G13909 is varied by the Revised  Regulatory Timetable attached as Appendix “B” to this Order     DATED at the City of Vancouverin the Province of British Columbiathis        21                 Attachments    Orders/G16609_FBC_2009 RDACOSA Revised Timetable   BRIT ISH  COLUMBIA   UTIL IT IES  COMMISS ION         ORDER    NUMBER   G16609        st             day of December 2009 BY ORDER  Original signed by Anthony JPullman  Panel Chair and Commissioner 
APPENDIX A  to Order G16609  Page xx of xx      FortisBC Inc.   Application for Approval of a   2009 Rate Design and Cost of Service Analysis    REASONS FOR DECISION  BACKGROUND    On October 302009 FortisBC Inc. (“FortisBC”) filed its 2009 Rate Design and Cost of Service Analysis model  pursuant to Sections 58 and 61 of the Utilities Commission Act.  The Application includes a Rate Designand an  accompanying Cost of Service Analysis (“COSA”), for which FortisBC seeks Commission approval   By letter to the Commission dated November 62009British Columbia Municipal Electric Utilities (“BCMEU”)  advised the Commission that it opposes the COSA and Rate Design proposed by FortisBC and states that a  Negotiated Settlement Process (“NSP”) is not the appropriate means of addressing COSA principles and rate  rebalancing   On November 262009the Commission issued Order G13909establishingamong other thingsa procedural  Conference and a Preliminary Regulatory Timetable for the Application   The Procedural Conference was held in Kelowna on December 152009In addition to the Applicantthe  following eight intervenors entered appearances and made oral submissions at the Procedural Conference BCMEU, Big White Ski Resort (“BWSR”), Roxul Inc., British Columbia Old Age Pensioners Organization et al  (“BCOAPO”), Zellstoff CelgarOkanagan Environmental Industry Alliance (“OEIA”), Alan Wait and Andy Shadrack The following issues were addressed   the nature of the regulatory processand   the regulatory timetable   PROCESS    FortisBC submitted that the process should comprise a NSP phase followed by a written processThe NSP would  cover any issues parties wished to negotiatebut FortisBC considered that allocation of Contract Demand was an  issue which it wished to be addressed in the NSP (T1:710).   
APPENDIX A  to Order G16609  Page xx of xx        All eight intervenors except Roxul Inc (which took no positionwere generally unsupportive of a NSPalthough  some acknowledged that such a process could be used for some parts of the Application.  BCMEU was in favour  of a NSP except on rate rebalancing issues (T1:12).  It submitted that it had spent two months negotiating with  FortisBC and had concluded that the differences between them required expert testimony to be filed and  challenged through an oral hearing process (T113). BCMEU submitted that allocation of Contract Demand was  a principle that has proved difficult to negotiate and questioned the efficiency of a NSP with a large number of  people pursuing a variety of issues (T1:38).    BWSR generally endorsed the BCMEU position that the matter proceed to an oral public hearing on COSA  matters (T1:16).  It submitted that a NSP would be inefficient and endorsed BCMEUs position (T1:16).    BCOAPO submitted that an oral hearing was “probably the way to go” (T1:18).     MrWait submitted he would prefer an oral hearing (T1:18).     OEIA submitted that it “…would be important to go through an oral hearingwe would support an oral hearing  versus an NSP” (T1:19).     MrShadrack submitted that his preference was for an oral hearing (T1:1920).     Zellstoff Celgar (T1:2023submitted its preference for an oral hearing for a number of reasons   It appears to be the ratepayer most affected by the Application Its consultations with FortisBC had led it to believe that costs would be allocated across the entire large  general service transmission class It is the only ratepayer on Rate schedule 33and  It is considering its position on having the Commission set its generation baseline        
APPENDIX A  to Order G16609  Page xx of xx      REGULATORY TIMETABLE    On the issue of the regulatory timetableFortisBC introduced a timetable which reflected its desire for a NSP followed by a written hearing (Exhibit B2), while all intervenors endorsed the Commission staffs’ strawman”  timetable (Exhibit A3). BCMEU submitted that the staff timetable would accommodate the expert it proposed  to call to the hearing   COMMISSION DETERMINATION    The Commission Panel notes that this will be FortisBCs first RDA since 1997 and that it has tried negotiation  with BCMEU to resolve the major issue and failedIt is also cognizant of the diversity of issues which must be  addressed which may not be adequately canvassed in a process that will most likely be dominated by two large  protagonists disputing a single issue.  To ensure that the Application is heard in a process that is transparent efficient and above all fair the Commission Panel determines that an oral hearing process is the appropriate  method of hearing the Application.  The Commission Panel therefore orders that the Application proceed by way  of an Oral Public Hearing commencing MondayMay 32010 at 9:00 a.min the City of Kelownaat a location to  be determined by further Order   The Commission Panel adopts the Commission staff timetable that was accepted by all Intervenors.  The  Preliminary Timetable attached as Appendix “A” to Order G13909 is varied accordingly      
  REVISED REGULATORY TIMETABLE      ACTION  FortisBC Response to Commission Information Request #1; FortisBC Response to Intervenor Information Request #1  Commission Information Request #2 to FortisBC Intervenor Information Request #2 to FortisBC  FortisBC Response to Commission Information Request #2; FortisBC Response to Intervenor Information Request #2  Intervenor Evidence  Information Requests on Intervenor Evidence  Intervenor Responses to Information Requests  Oral Hearing Commences       APPENDIX B  to Order G16609  Page 1 of 1      DATE  MondayJanuary 182010 MondayFebruary 012010 TuesdayMarch 22010 MondayMarch 152010 MondayMarch 292010 ThursdayApril 152010 MondayMay 032010