LETTER NO. L‐111‐09
ERICA M. HAMILTON
SIXTH FLOOR, 900 HOWE STREET, BOX 250
COMMISSION SECRETARY
VANCOUVER, B.C. CANADA V6Z 2N3
Commission.Secretary@bcuc.com
TELEPHONE: (604) 660‐4700
web site: http://www.bcuc.com
BC TOLL FREE: 1‐800‐663‐1385
FACSIMILE: (604) 660‐1102
Log No. 30899
VIA E‐MAIL
cdonohue@png.ca
December 8, 2009
PNG‐WEST
2010 REVENUE REQUIREMENTS EXHIBIT A‐5
Mr. Craig P. Donohue
Director, Regulatory Affairs and Gas Supply
Pacific Northern Gas Ltd.
1185 West Georgia Street
Vancouver, BC V6E 4E6
Dear Mr. Donohue:
Re: Pacific Northern Gas Ltd.
Project No. 3698578/Order G‐130‐09
2010 Revenue Requirements Application
In order to accommodate the dates available for the participants, the Commission has revised the Regulatory
Timetable enclosed with Letter No. L‐108‐09 (Exhibit A‐4) and issues a Revised Regulatory Timetable as set out
in Appendix A to this Letter. The PNG‐West Negotiated Settlement Process will commence on Monday,
February 8, 2010 with PNG (N.E.) to follow immediately thereafter.
Yours truly,
Original signed by:
Erica M. Hamilton
CMcM/dg
Attachment
cc: Registered Intervenors – PNG 2010RR
(PNG‐2010RR‐RI)
PF/PNGW/GenCor/2009RR/A‐5_Revised Regulatory_Timetable
Pacific Northern Gas Ltd.
Application for Approval of 2010 Revenue Requirements
for the PNG‐West Service Area
REVISED REGULATORY TIMETABLE
ACTION
Commission and Intervenor IRs No. 2, if necessary
PNG Responses to Commission and Intervenor IRs No. 2
Negotiated Settlement Process Commences
APPENDIX A
to Letter No. L‐111‐09
Page 1 of 1
DATES (2009/2010)
Friday, December 11
Friday, December 18
Monday, February 8
You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.