IN THE MATTER OF

the Utilities Commission Act, R.S.B.C. 1996, Chapter 473

 

and

 

An Application by British Columbia Hydro and Power Authority

Residential Inclining Block Rate Re-pricing Application

 

 

BEFORE:               L.F. Kelsey, Commissioner                                           December 22, 2010

 

 

O  R  D  E  R

 

WHEREAS:

 

A.      British Columbia Hydro and Power Authority (BC Hydro) filed its Residential Inclining Block (RIB) Re-pricing Application (Application) with the British Columbia Utilities Commission (Commission), pursuant to sections 58 to 61 of the Utilities Commission Act, for approval of a pricing principle for its RIB rate, to be effective April 1, 2011;

 

B.      The RIB rate was originally approved by Commission Order G-124-08 issued on October 1, 2008, with approval of a pricing principle for only two years, F2009 and F2010.  Commission Order G-47-10 issued on March 15, 2010 granted approval for BC Hydro to apply its interim F2011 rate increase uniformly across the RIB rate’s Basic Charge, the Step-1 rate, and Step-2 rate.  The F2011 pricing principle applicable to the RIB rate was approved by Commission Order G-180-10 which approved the BC Hydro F2011 Revenue Requirements application Negotiated Settlement Agreement;

 

C.      In this Application, BC Hydro proposes that the pricing principle approved in Orders G-47-10 and G-180-10 in regard to F2011 be sustained until such time as circumstances require that it be re-visited, and in any case no sooner than the final resolution of its Time-of-Use rate application which is currently under preparation and the provincial government’s approval of BC Hydro’s 2011 Integrated Resource Plan.  In short, BC Hydro requests approval to allow it to continue to apply the revenue requirement rate increases to each of the RIB rate’s Basic charge, Step 1 Rate and Step 2 Rate;

 

D.      BC Hydro proposes that the application be reviewed by a written hearing process.

 


 

 

NOW THEREFORE the Commission orders as follows:

 

1.       The Application will be reviewed by a Written Hearing Process.  The Regulatory Timetable is in Appendix A to this Order.

 

2.       The process will include one round of Information Requests from Commission staff and Registered Interveners and written submissions from BC Hydro and Registered Interveners.

 

3.       BC Hydro is to provide a copy of the Application and this Commission Order and Regulatory Timetable to those who were Interveners in the 2008 RIB application proceeding.

 

4.       Those who wish to participate in BC Hydro’s RIB Re-pricing Application are to advise the Commission Secretary of their intention to do so, in writing no later than Thursday, January 6, 2011.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this            23rd           day of December 2010.

                                                                                                                               

                                                                                                                                BY ORDER

 

                                                                                                                                Original signed by:

 

                                                                                                                                L.F. Kelsey

                                                                                                                                Commissioner

 


British Columbia Hydro and Power Authority

Residential Inclining Block Rate Re-pricing Application

 

 

REGULATORY TIMETABLE

 

 

 

                                ACTION                                                                                                                        DATES (2011)

 

Intervener Registration Deadline                                                                                              Thursday, January 6

 

Application Deadline for Participant Funding                                                                       Tuesday, January 11

 

Commission and Intervener Information Requests No. 1                                               Monday, January 17

 

BC Hydro Responses to Information Requests No. 1                                                        Monday, February 7

 

Intervener Submissions                                                                                                                Friday, February 18

 

BC Hydro Submissions                                                                                                                   Friday, February 25

 

 

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.