Via Email
November 30, 2010
To: FortisBC Inc.
Registered Interveners
(FBC-2009RD-RI)
Re: FortisBC Inc.
Project No. 3698564/Order G-139-09
2009 Rate Design Application and Cost of Service Study
COSA Re-filing Pursuant to Commission Order G-156-10
In accordance with Directive 3 of British Columbia Utilities Commission (Commission) Order G-156-10, FortisBC filed a Cost of Service Analysis (COSA) Update in electronic format, together with a summary of the resulting Revenue-to-Cost ratios with the Commission on November 19, 2010. In the covering letter accompanying the filing, FortisBC states it expects that the Interveners in the 2009 COSA and Rate Design Proceeding will wish to provide comment on the summary and the electronic copy of the COSA Update.
Interveners who wish to make comments on either the COSA Update or the summary must file their comments in writing with the Commission on or before 5:00 p.m., Monday, December 6, 2010. Interveners are to confine their comments to whether the COSA Update complies with Directive 3. FortisBC must file a reply, if necessary, by 5:00 p.m., Thursday, December 9, 2010.
Yours truly,
Erica M. Hamilton
AR/yl