IN THE MATTER OF

the Utilities Commission Act, R.S.B.C. 1996, Chapter 473

 

and

 

Application by British Columbia Hydro and Power Authority

for a Certificate of Public Convenience and Necessity

to Construct and Operate the Ruskin Dam and Powerhouse Upgrade Project

 

BEFORE:               M.R. Harle, Panel Chair/Commissioner

                                N.E. MacMurchy, Commissioner                               September 14, 2011

                                A.W.K. Anderson, Commissioner

 

 

O R D E R

WHEREAS:

 

A.    On February 22, 2011, British Columbia Hydro and Power Authority (BC Hydro) filed pursuant to section 46(1) of the Utilities Commission Act (the Act), an application for a Certificate of Public Convenience and Necessity (CPCN) to construct and operate the Ruskin Dam and Powerhouse Upgrade Project (the Project) as described in the Application;

 

B.    By Order G-34-11, the British Columbia Utilities Commission (Commission) established a Written Public Hearing process for the review of the Application having two rounds of Information Requests according to the Regulatory Timetable as set out in Appendix A to that Order;

 

C.    By letter dated March 29, 2011, BC Hydro applied for a revision to the Regulatory Timetable.  BC Hydro circulated a draft copy of the proposed changes to the Regulatory Timetable to all Interveners in the Proceeding on Friday, March 25, 2011 and no Intervener raised any concerns;

 

D.    By Order G-65-11 the Commission approved BC Hydro’s request for a revised Regulatory Timetable as set out in Appendix A to that Order;

 

E.    By letter dated April 21, 2011, the Commission received a request from counsel for the Kwantlen First Nation to amend the Regulatory Timetable to extend the date for filing Intervener Evidence.  The letter further stated Kwantlen’s counsel had canvassed BC Hydro and Interveners and no concerns were raised;

 

F.    By Order G-76-11 the Commission approved the Kwantlen First Nation’s request for a revised Regulatory Timetable as set out in Appendix A to that Order;

G.   By letter dated June 23, 2011, BC Hydro requested an amendment to the Regulatory Timetable.  BC Hydro heard no objections to the proposed amendment from Interveners;

 

H.    By Order G-116-11 the Commission approved BC Hydro’s request to amend the Regulatory Timetable as set out in Appendix A to that Order;

 

I.     By letter dated September 2, 2011, BC Hydro requested an amendment to the Regulatory Timetable.

BC Hydro heard no objections to the proposed amendment from Interveners;

 

J.     The Commission has reviewed the request and determined that changes to the Regulatory Timetable are required to the timetable suggested by BC Hydro.

 

 

NOW THEREFORE the Commission orders that the Written Public Hearing process for the review of the Application is amended according to the Regulatory Timetable as set out in Appendix A to this Order.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this        14th          day of September 2011.

 

                                                                                                                                BY ORDER

 

Original signed by:

 

                                                                                                                                M.R. Harle

                                                                                                                                Panel Chair/Commissioner

 

Attachment

 


 

 

 

Application by British Columbia Hydro and Power Authority

for a Certificate of Public Convenience and Necessity

to Construct and Operate the Ruskin Dam and Powerhouse Upgrade Project

 

 

 

 

AMENDED REGULATORY TIMETABLE

 

 

 

 

ACTION

DATE (2011)

BC Hydro submits Rebuttal Evidence, Evidentiary Update and its responses to Exhibits A-13 IRs and A-14

 

Wednesday, September 21

 

Procedural Conference, if warranted, with respect to process for the adequacy of consultation with Kwantlen

 

Thursday, September 29

IRs on BC Hydro Rebuttal Evidence/Evidentiary Update/Exhibits A-13 and A-14 responses

 

Friday, October 7

BC Hydro responses to IRs on BC Hydro Rebuttal Evidence/Evidentiary Update/Exhibits A-13 and A-14 responses

 

Friday, November 4

 

BC Hydro Final Written Submission

Friday, November 25

 

Intervener Final Written Submission

Monday, December 12

 

BC Hydro Written Reply Submission

Friday, December 23

 

 