IN THE MATTER OF

the Utilities Commission Act, R.S.B.C. 1996, Chapter 473

 

and

 

An Application by British Columbia Hydro and Power Authority

for a Certificate of Public Convenience and Necessity for the

Dawson Creek/Chetwynd Area Transmission Project

 

 

BEFORE:               L.A. O’Hara, Panel Chair/Commissioner

                                C.A. Brown, Commissioner                                          September 15, 2011

D. Morton, Commissioner

 

 

O  R  D  E  R

 

WHEREAS:

 

A.    On July 11, 2011, British Columbia Hydro and Power Authority (BC Hydro) applied (the Application) pursuant to subsection 46(1) of the Utilities Commission Act to the British Columbia Utilities Commission (the Commission) for a Certificate of Public Convenience and Necessity to construct and operate the Dawson Creek/Chetwynd Area Transmission Project as described in the Application;

 

B.    By Order G-132-11, the Commission established an Initial Regulatory Timetable and Procedural Conference for the review of the Application.

 

C.    By letter dated September 13, 2011, BC Hydro requested an amendment to the Regulatory Timetable.

 

D.    The Commission has reviewed the request and determined that changes to the Regulatory Timetable are required.

 

 

NOW THEREFORE the Commission orders that:

 

1.    The Regulatory Timetable for the review of the Application is amended as set out in Appendix A to this Order.


 

2.    The Procedural Conference regarding the further regulatory process for the review of the Application has been rescheduled from September 22, 2011 to November 4, 2011, commencing at 9:00 a.m. in the Commission’s Hearing Room on the 12th Floor, 1125 Howe Street, Vancouver, BC.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this            15th         day of September 2011.

 

                                                                                                                                BY ORDER

 

                                                                                                                                Original signed by:

 

                                                                                                                                L.A. O’Hara

                                                                                                                                Commissioner

Attachment

 


 

An Application by British Columbia Hydro and Power Authority

for a Certificate of Public Convenience and Necessity for the

Dawson Creek/Chetwynd Area Transmission Project

 

 

 

 

 

AMENDED REGULATORY TIMETABLE

 

 

BC Hydro Response to Commission Information Requests No. 1

 

 

Thursday, September 15, 2011

 

BC Hydro Response to Intervener Information Request No. 1

 

 

Thursday, September 22, 2011

 

Participation Assistance/Cost Award Budget Submissions

 

 

 

Monday, October 3, 2011

Commission and Intervener Information Request No. 2

 

Thursday, October 6, 2011

 

BC Hydro Responses to Information Request No. 2

 

Thursday, October 27, 2011

 

Intervener Statement of Intent to File Evidence

 

 

Wednesday, November 2, 2011

Procedural Conference

Friday, November 4, 2011

 

 