Via Email
larry_h42@hotmail.com September 23, 2011
terrychristinestamper@yahoo.com
|
|
Birds Eye Cove - CPCN Revenue Requirements & Tariff Exhibit A-23 |
|
Mr. Larry Higginson Birds Eye Cove Estates Ltd. Box 355 Burns Lake, BC V0J 1E0 |
Mr. H.T. Stamper Cove Power Society 6792 Stoneyhill Road Duncan, BC V9L 2Y2 |
Dear Mr. Higginson and Mr. Stamper:
Re: Birds Eye Cove Estates Ltd.
Project No. 3698589
Application for a Certificate of Public Convenience and Necessity
Revenue Requirements and Tariffs
Extension of Regulatory Timetable
On September 20, 2011, Cover Power Society filed a letter requesting the British Columbia Utilities Commission (Commission) grant a further extension of the Regulatory Timetable for the review of the Application by Birds Eye Cove Estates Ltd. (BECE) to after February 15, 2012, to allow more time to complete the sale. By email dated September 21, 2011, BECE supported the request for an extension.
As the parties are making progress on arrangements for the sale of Birds Eye Cove Power, the Commission grants the request to extend the date of BECE’s written final submission to Wednesday, February 29, 2012 and amends the Regulatory Timetable attached as Appendix A to this letter.
Yours truly,
Alanna Gillis
JBW/dd
Enclosure
cc: Registered Interveners
(Birds Eye-RI)
Birds Eye Cove Estates Ltd.
An Application by for a Certificate of Public Convenience and Necessity
and Approval of Revenue Requirements and Electric Tariff
REGULATORY TIMETABLE
|
ACTION |
DATES (2012) |
|
BECE Written Final Submission |
Wednesday, February 29 |
|
Intervener Written Final Submissions |
Wednesday, March 14 |
|
BECE Written Reply Submission |
Wednesday, March 28 |