Via Email

                                                                                                                                February 14, 2012

 

 

BC Hydro - F2012-F2014

Revenue Requirements                     Exhibit A-26

 

TO:         British Columbia Hydro and Power Authority

                Registered Interveners

 

Re:  British Columbia Hydro and Power Authority

Project No. 3698622/Order G-40-11

F2012 to F2014 Revenue Requirements Application

 

The British Columbia Utilities Commission’s (Commission) has received the following seven requests for an extension to the filing date for Information Request No. 2 (IR No. 2) as set out in Order G-206-11 (Exhibit A-18):

 

         Clean Energy Association of British Columbia

         Association of Major Power Customers of BC

         Canadian Office and Professional Employees Union Local 378

         BC Sustainable Energy Association and Sierra Club British Columbia

         British Columbia Old Age Pensioners’ Organization et al.

         Energy Solutions for Vancouver Island Society

         Mr. Terry Vulcano

 

Based on the number of Interveners requesting an extension to the filing date for IR No. 2 the Commission Panel considers providing a one week extension for the Commission and all Interveners is warranted.  The Amended Regulatory Timetable is attached as Appendix A.

 

                                                                                                                                Yours truly,

 

                                                                                                                                Alanna Gillis

 

cms

Attachment

 


 

British Columbia Hydro and Power Authority

Amended F2012 to F2014 Revenue Requirements Application

 

 

AMENDED REGULATORY TIMETABLE

 

 

ACTION

DATE

Commission and Intervener Information Request No. 2

Tuesday, March 6, 2012

BC Hydro Information Request No. 2 Responses

Tuesday, March 27, 2012

Intervener Evidence

Tuesday, April 10, 2012

Commission and Participants Information Request No. 1 on Intervener Evidence

Tuesday, April 24, 2012

Intervener Evidence Information Request No. 1 Responses

Tuesday, May 8, 2012

BC Hydro Rebuttal Evidence

Tuesday, May 15, 2012

Procedural Conference No. 4 (if necessary)

Friday, May 18, 2012

Commencement of Negotiated Settlement Process (if any)
(anticipated duration:  up to one week)

Monday, May 28, 2012

Commencement of Oral Public Hearing
(anticipated duration:  two to three weeks)

Monday, June 18, 2012

 