Via Email
February 14, 2012
|
|
BC Hydro - F2012-F2014 Revenue Requirements Exhibit A-26 |
TO: British Columbia Hydro and Power Authority
Registered Interveners
Re: British Columbia Hydro and Power Authority
Project No. 3698622/Order G-40-11
F2012 to F2014 Revenue Requirements Application
The British Columbia Utilities Commission’s (Commission) has received the following seven requests for an extension to the filing date for Information Request No. 2 (IR No. 2) as set out in Order G-206-11 (Exhibit A-18):
• Clean Energy Association of British Columbia
• Association of Major Power Customers of BC
• Canadian Office and Professional Employees Union Local 378
• BC Sustainable Energy Association and Sierra Club British Columbia
• British Columbia Old Age Pensioners’ Organization et al.
• Energy Solutions for Vancouver Island Society
• Mr. Terry Vulcano
Based on the number of Interveners requesting an extension to the filing date for IR No. 2 the Commission Panel considers providing a one week extension for the Commission and all Interveners is warranted. The Amended Regulatory Timetable is attached as Appendix A.
Yours truly,
Alanna Gillis
cms
Attachment
British Columbia Hydro and Power Authority
Amended F2012 to F2014 Revenue Requirements Application
AMENDED REGULATORY TIMETABLE
|
ACTION |
DATE |
|
Commission and Intervener Information Request No. 2 |
Tuesday, March 6, 2012 |
|
BC Hydro Information Request No. 2 Responses |
Tuesday, March 27, 2012 |
|
Intervener Evidence |
Tuesday, April 10, 2012 |
|
Commission and Participants Information Request No. 1 on Intervener Evidence |
Tuesday, April 24, 2012 |
|
Intervener Evidence Information Request No. 1 Responses |
Tuesday, May 8, 2012 |
|
BC Hydro Rebuttal Evidence |
Tuesday, May 15, 2012 |
|
Procedural Conference No. 4 (if necessary) |
Friday, May 18, 2012 |
|
Commencement of Negotiated
Settlement Process (if any) |
Monday, May 28, 2012 |
|
Commencement of Oral Public
Hearing |
Monday, June 18, 2012 |