IN THE MATTER OF

the Utilities Commission Act, R.S.B.C. 1996, Chapter 473

 

and

 

FortisBC Energy Inc.

Application for an Extension of the Operating Agreement

with the District of Elkford

 

BEFORE:                 L.F. Kelsey, Commissioner

                                C.A. Brown, Commissioner

                                N.E. MacMurchy, Commissioner                                       December 12, 2013

                                B.A. Magnan, Commissioner

                                D.M. Morton, Commissioner

                                R.D. Revel, Commissioner

 

O  R  D  E  R

WHEREAS:

 

A.       On November 1, 1992, FortisBC Energy Inc. (FEI), formerly BC Gas Inc., entered into a Franchise Agreement with the District of Elkford (Municipality);

 

B.       The Franchise Agreement expired October 23, 2013;

 

C.       On November 18, 2013, FEI applied to the British Columbia Utilities Commission (Commission) for approval of an Amending Agreement (Application) that extends the term of the Franchise Agreement to March 31, 2014;

 

D.       The Commission reviewed the Application and considers that approval is warranted.

 

 

NOW THEREFORE the Commission, pursuant to Section 45 of the Utilities Commission Act, approves the Amending Agreement as filed.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this      12th        day of December 2013.

 

                                                                                                                                BY ORDER

 

Original signed by:

 

D.M. Morton

                                                                                                                                Commissioner

 