IN THE MATTER OF
the Utilities Commission Act, R.S.B.C. 1996, Chapter 473

 

and

 

An Application by FortisBC Inc.

for a Certificate of Public Convenience and Necessity

for the Purchase of the Utility Assets of the City of Kelowna

Phase 2

 

 

BEFORE:               D.M. Morton, Panel Chair/Commissioner

                                A.A. Rhodes, Commissioner                                                        August 7, 2013

                                B.A. Magnan, Commissioner

 

 

O  R  D  E  R

 

WHEREAS:

A.      On November 13, 2012, FortisBC Inc. (FortisBC) filed an application with the British Columbia Utilities Commission (Commission) pursuant to sections 45 and 46 of the Utilities Commission Act (Act) for  a Certificate of Public Convenience and Necessity (CPCN), for an extension of its distribution system resulting from its purchase of the electricity distribution assets of the City of Kelowna (Transaction), and further sought an order pursuant to sections 59 and 60 of the Act to include the impact of the Transaction in its revenue requirements (Original Application);

B.      The Commission determined on Day 1 of the Oral Hearing for the Original Application that it considered potential rate discrimination issues to be within the scope of the proceeding and subject to a second Phase process;

C.      By Order C-4-13 dated March 1, 2013, the Commission approved FortisBC’s Original Application subject to certain conditions;

D.      On April 18, 2013, the Commission issued a letter to FortisBC, potential interveners and interested parties, informing these parties that a Phase 2 process will take place to address issues of potential rate discrimination arising from Tolko Industries Ltd. (Tolko) now becoming a direct customer of FortisBC (Phase 2 Application).  Additionally, it was determined that FortisBC would remain as the Applicant for the Phase 2 process;

E.       The following Interveners registered to participate in the Phase 2 Application: Tolko, Zellstoff Celgar Limited Partnership (Celgar), British Columbia Hydro and Power Authority (BC Hydro), B.C. Sustainable Energy Association (BCSEA), British Columbia Pensioners’ and Seniors’ Organization et al. (BCPSO), and Norman Gabana;

F.       By Order G-111-13 dated July 25, 2013, and as set out in the July 24, 2013 Procedural Conference, the Commission established that the Phase 2 Application would be heard by way of a written hearing with a further regulatory timetable to be issued in due course.  In addition, the Commission determined the scope for the Phase 2 Application and established an arrangement to address Celgar’s concern regarding unanswered Information Requests (IRs) issued to BC Hydro;

G.     On August 2, 2013, BC Hydro submitted a letter to the Commission indicating that an agreement had been reached between itself and Celgar and filed responses to the agreed upon IRs.

 

 

NOW THEREFORE the Commission issues the Final Regulatory Timetable attached as Appendix A to this Order.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this            7th                   day of August 2013.

 

                                                                                                                                BY ORDER

 

                                                                                                                                Original Signed By:

 

D.M. Morton

Commissioner

Attachment



 

FORTISBC INC.

Application for a Certificate of Public Convenience and Necessity

for the Purchase of the Utility Assets of the City of Kelowna

Phase 2

 

 

 

FINAL REGULATORY TIMETABLE

 

 

 

ACTION

DATE (2013)

Celgar Final Submission

Thursday, August 22

Other Parties Final Submission

Thursday, August 29

Celgar Reply Submission

Thursday, September 5

 

 