Via Email
bchydroregulatorygroup@bchydro.com January 31, 2013
|
|
BC Hydro Application to Amend TS No 74 (GBL) Exhibit A-4 |
Ms. Janet Fraser
Chief Regulatory Officer
British Columbia Hydro and Power Authority
17th Floor, 333 Dunsmuir Street
Vancouver, BC V6B 5R3
Dear Ms. Fraser:
Re: British Columbia Hydro and Power Authority
Application to Amend Tariff Supplement No. 74
Customer Baseline Load Determination Guidelines for RS 1823
Customers with Self-Generation Facilities
Further to Order G-172-12 the Commission has determined that a second round of Information Requests is necessary and has established a further Preliminary Regulatory Timetable for this proceeding.
PRELIMINARY REGULATORY TIMETABLE
|
ACTION |
DATE (2013) |
|
Commission and Intervener Information Request No. 2 to BC Hydro |
Monday, February 18 |
|
BC Hydro responds to Commission and Intervener Information Request No. 2 |
Friday, March 8 |
The Commission will issue a further regulatory order to establish the remaining process in due course.
Yours truly,
Erica Hamilton
CMM/sk
cc: BC Hydro Application to Amend TS No. 74 (GBL)