Via Email
September 5, 2013
|
|
FEU Common Rates, Amalgamation Rate Design Reconsideration Phase 2 Exhibit A-10 |
To: FortisBC Energy Inc.
Commercial Energy Consumers of BC
Registered Interveners
(FEU-RD-Phase2-RI)
Re: Applications for Reconsideration and Variance
of Order G-26-13 dated February 25, 2013
in respect of FortisBC Energy Utilities’
Common Rates, Amalgamation and Rate Design Application
Project No. 3988717/Order G-100-13
Further to submission received in response to Commission letter L-46-13 (Exhibit A-7), enclosed please find further amended Regulatory Timetable attached as Appendix A.
Yours truly,
Erica Hamilton
KB/dg
Attachment
Applications for Reconsideration and Variance
of Order G-26-13 dated February 25, 2013
in respect of FortisBC Energy Utilities’
Common Rates, Amalgamation and Rate Design Application
AMENDED REGULATORY TIMETABLE
|
ACTION |
DATE (2013) |
|
FEU, CEC Rebuttal Evidence on Intervener Evidence – If any |
Wednesday, September 25 |
|
FEU, CEC Final Submissions |
Wednesday, October 9 |
|
Intervener Final Submissions |
Wednesday, October 23 |
|
FEU, CEC Reply Submissions |
Wednesday, November 6 |