Orders

Decision Information

Decision Content

 

ORDER NUMBER

G-240-19

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

British Columbia Utilities Commission

Indigenous Utilities Regulation Inquiry

 

BEFORE:

D. M. Morton, Panel Chair

C. M. Brewer, Commissioner

A. K. Fung, QC, Commissioner

E. B. Lockhart, Commissioner

 

on October 7, 2019

 

ORDER

WHEREAS:

 

A.      On March 11, 2019, by Order in Council (OIC) No. 108, made pursuant to section 5(1) of the Utilities Commission Act (UCA), the Lieutenant Governor in Council directed the British Columbia Utilities Commission (BCUC) to advise the Lieutenant Governor in Council respecting the regulation of Indigenous utilities in accordance with the terms of reference set out in section 3 of OIC No. 108 (Indigenous Utilities Regulation Inquiry);

B.      Section 3 of OIC No. 108 also provides that the BCUC must submit reports to the minister responsible for the Hydro and Power Authority Act, as follows:

1.       An interim report describing the BCUC's progress to date and the BCUC’s preliminary findings must be submitted no later than December 31, 2019; and

2.       A final report describing the results of consultations undertaken by the BCUC and the BCUC's findings and recommendations must be submitted no later than January 31, 2020;

C.      By Order G-62-19 dated March 19, 2019, the BCUC established the Indigenous Utilities Regulation Inquiry;  

D.      By Order G-214-19 dated September 6, 2019, the BCUC issued a regulatory timetable for the Inquiry; and

E.       The BCUC considers that an amendment to the regulatory timetable for the Inquiry is warranted

 


 

NOW THEREFORE the BCUC amends the regulatory timetable established by Order G-214-19. The amended regulatory timetable is attached as Appendix A to this order.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this             7th              day of October 2019.

 

BY ORDER

 

Original signed by:

 

D. M. Morton

Commissioner

 

 

Attachment

 

 


British Columbia Utilities Commission

Indigenous Utilities Regulation Inquiry

 

REGULATORY TIMETABLE

 

Action

Date (2019)

Draft report issued for comment

Friday, November 1

Workshop – Prince George, Coast Inn of the North

Monday, November 18

Workshop – Kelowna, Sandman Hotel

Thursday, November 21

Workshop – Vancouver, Allwest Reporting
(12th Floor, 1125 Howe St)

Wednesday, November 27

Workshop – Nanaimo, Coast Bastion Hotel

Thursday, November 28

Workshop1 – Victoria, Comfort Inn & Suites

Friday, November 29

Workshop1 – Smithers, Hudson Bay Lodge

Monday, December 9, 2019

Participant comments on draft report

Tuesday, December 31, 2019

Interim Report issued to minister responsible for

the Hydro and Power Authority Act

Tuesday, December 31, 2019

Final Report issued to minister responsible for the

Hydro and Power Authority Act

Friday, January 31, 2020

 

1Please note that the Victoria and Smithers workshops are additions since the last regulatory timetable.

 

Format of the Workshops

Each workshop will begin with a BCUC Panel or staff presentation providing an overview of the Inquiry’s Draft Report. Following the presentation, staff will be available to answer any initial questions. Participants will then divide into smaller groups to work through the report and collect thoughts and suggestions with support from BCUC Staff and Four Directions Management Services as facilitators.

 

Later in the sessions, each small group will select a representative to present a summary of its feedback to the Panel. Individuals will also have an opportunity to address the Panel and add any items that are not captured in the group summary. The feedback to the Panel will be transcribed by Allwest Reporting and transcripts will be added to the Inquiry’s proceeding page on https://www.bcuc.com/.

 

 

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.