ORDER NUMBER

R-30-19

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

British Columbia Hydro and Power Authority

Notice of Penalty

for the Contravention of Mandatory Reliability Standards

Identified as:

Violation 1

CIP-002-1

Violation ID: BCUC2017000605

Violation 2

CIP-005-3a

Violation ID: BCUC2017000607

Violation 3

CIP-006-1

Violation ID: BCUC2017000603

Violation 4

CIP-007-3a

Violation ID: BCUC2017000604

 

BEFORE:

D. M. Morton, Panel Chair

W. M. Everett, QC, Commissioner

A. K. Fung, QC, Commissioner

 

on November 26, 2019

 

ORDER

WHEREAS:

 

A.      On October 2, 2019, the British Columbia Utilities Commission (BCUC) issued a confidential order and Notice of Penalty to British Columbia Hydro and Power Authority (BC Hydro) for the four Critical Infrastructure Protection (CIP) standard contraventions of Mandatory Reliability Standards noted above;

B.      On October 2, 2019, the BCUC ordered BC Hydro to make submissions with respect to the release of confidential materials from this proceeding;

C.      On October 25, 2019, BC Hydro stated in a letter that it was not opposed to making public a redacted version of the Notice of Penalty; and

D.      Following review of BC Hydro’s submission, the Panel considers the release of the redacted Notice of Penalty to the general public is warranted.

 

NOW THEREFORE pursuant to section 125.2(10) and Part 8.1 of the UCA, the BCUC orders the following:

 

1.       The release of the redacted Notice of Penalty to the general public, as contained in Appendix A.

2.       All related material filed in this proceeding shall be held confidential, unless otherwise ordered by the BCUC, given the intent of Critical Infrastructure Protection (CIP) standards is to protect the bulk electric system against cybersecurity compromises that could lead to misoperation or instability, and that information related to an Entity’s non-compliance with CIP standards could potentially be used to compromise or disrupt the bulk electric system.

 

DATED at the City of Vancouver, in the Province of British Columbia, this          26th            day of November 2019.

 

BY ORDER

 

Original Signed By:

 

D. M. Morton

Commissioner

 

 