ORDER NUMBER

G-300-20

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

British Columbia Hydro and Power Authority

Long-Term Resource Plan Filing Date

 

BEFORE:

D. M. Morton, Panel Chair

C. M. Brewer, Commissioner

R. I. Mason, Commissioner

November 27, 2020

 

ORDER

WHEREAS:

 

A.      By Order G-205-20 dated July 30, 2020, the British Columbia Utilities Commission (BCUC) established a regulatory timetable for the review of British Columbia Hydro and Power Authority (BC Hydro) long-term resource plan filing date and ordered that by August 20, 2020 BC Hydro submit to the BCUC, with rationale:

1.       the date by which BC Hydro will file its next long-term resource plan; and

2.       a proposal for an interim filing of BC Hydro’s current planning context that would, in the absence of a recently filed long-term resource plan, aid in the review of BC Hydro applications filed prior to the BCUC review of the next BC Hydro long-term resource plan;

B.      By letter dated August 20, 2020, BC Hydro submits that it plans to file its next long-term resource plan in September 2021 (BC Hydro Proposal). Additionally, BC Hydro proposed to file in October 2020, a summary of the default inputs that BC Hydro will be using for consultation and in Spring 2021, a draft long-term resource plan;

C.      By September 3, 2020, interveners filed their submissions on the BC Hydro Proposal. On September 17, 2020, BC Hydro filed its reply submission;

D.      By letter dated September 25, 2020, BC Hydro requested that the BCUC suspend the proceeding until 30 days after the Government of BC has been sworn-in and a Cabinet has been appointed;

E.       By letter dated October 2, 2020, BC Hydro provided further submission. On October 6, 2020, interveners filed submissions on BC Hydro’s request to suspend the proceeding and BC Hydro filed a reply submission on October 8, 2020;

F.       By Order G-260-20 dated October 19, 2020, the BCUC directed BC Hydro to file a supplementary submission with regard to a filing date for the 2021 Integrated Resource Plan and a proposal for an interim filing of BC Hydro’s current planning context, 30 days after the Government of BC has been sworn-in and a Cabinet has been appointed. BC Hydro must also include an update on its 2021 Integrated Resource Plan timeline at this time;

G.      On November 26, 2020, the Cabinet for the Government of BC was sworn in; and

H.      The BCUC determines that establishing an updated regulatory timetable is warranted.

 

NOW THEREFORE the BCUC orders an updated regulatory timetable is established, attached as Appendix A to this order.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this              27th          day of November 2020.

 

BY ORDER

 

Original signed by:

 

D. M. Morton

Commissioner

 

 

Attachment

 

 


British Columbia Hydro and Power Authority

Long-Term Resource Plan Filing Date

 

REGULATORY TIMETABLE

 

 

Action

Date

BC Hydro supplementary submission

Monday, December 28, 2020

Intervener submissions

Monday, January 11, 2021

BC Hydro reply submission

Monday, January 18, 2021

 