ORDER NUMBER
G-284-22
IN THE MATTER OF
the Utilities Commission Act, RSBC 1996, Chapter 473
and
British Columbia Hydro and Power Authority
Fiscal 2023 to Fiscal 2025 Revenue Requirements Application
BEFORE:
D. M. Morton, Panel Chair
A. K. Fung, KC, Commissioner
R. I. Mason, Commissioner
A. Pape-Salmon, Commissioner
on October 12, 2022
ORDER
WHEREAS:
A. On August 31, 2021, the British Columbia Hydro and Power Authority (BC Hydro) filed its Fiscal 2023 to Fiscal 2025 Revenue Requirements Application (Application) with the British Columbia Utilities Commission (BCUC) pursuant to sections 44.2, and 58 to 61 of the Utilities Commission Act requesting, among other things, interim and, after certain future determinations in other proceedings, permanent approval of the following:
(i) Increase in rates by 0.62 percent, effective April 1, 2022, by 0.97 percent, effective April 1, 2023 and by 2.18 percent, effective April 1, 2024; and
(ii) The fiscal 2023, fiscal 2024, and fiscal 2025 Open Access Transmission Tariff rates as set out in Table 9-4 of the Application;
B. In the Application, BC Hydro also requested to set the Deferral Account Rate Rider on an interim and permanent basis at (2.0) percent, effective April 1, 2022 for fiscal 2023; and, on a permanent basis at (1.0) percent, effective April 1, 2023 for fiscal 2024 and (0.5) percent, effective April 1, 2024 for fiscal 2025;
C. By Order G-239-22 the BCUC established an amended regulatory timetable for the review of the Application, which included, among other items, an oral hearing, BC Hydro’s and interveners’ written final arguments and BC Hydro’s written reply argument;
D. During the oral hearing, the Panel canvassed parties on whether all or some portion of final arguments should be held orally; and
E. The BCUC has considered the submissions made by the parties at the oral hearing and finds that an amended regulatory timetable for the review of the Application is warranted.
NOW THEREFORE the BCUC amends the regulatory timetable to accommodate a potential oral phase of argument, as set out in Appendix A to this order.
DATED at the City of Vancouver, in the Province of British Columbia, this 12th day of October 2022.
BY ORDER
Original signed by:
D. M. Morton
Commissioner
Attachment
British Columbia Hydro and Power Authority
F2023 to F2025 Revenue Requirements Application
REGULATORY TIMETABLE
| Action
|
Date (2022)
|
| BC Hydro Written Final Argument |
Thursday, October 27 |
| Intervener Written Final Arguments |
Thursday, November 24 |
| BC Hydro Written Reply Argument |
Thursday, December 22 |
| Action
|
Date (2023)
|
| BCUC Decision on the Oral Phase of Argument and the scope |
On or before Tuesday, January 3 |
| Oral Phase of Argument* |
Monday, January 16 |
*Details regarding the Oral Phase of Argument will be provided in due course.