ORDER NUMBER
G-243-24
IN THE MATTER OF
the Utilities Commission Act, RSBC 1996, Chapter 473
and
FortisBC Energy Inc.
Cancellation of Tariff Supplement J-36 Fueling Services Agreement
between FEI and DanFoss Industries Ltd.
BEFORE:
B. A. Magnan, Commissioner
on September 16, 2024
ORDER
WHEREAS:
A. On September 5, 2024, FortisBC Energy Inc. (FEI) applied to the British Columbia Utilities Commission (BCUC), pursuant to sections 59 to 61 of the Utilities Commission Act (UCA), for approval of the cancellation of Tariff Supplement J-36 containing the fueling services agreement between FEI and DanFoss Industries Ltd. (DanFoss) to receive Compressed Natural Gas (CNG) fueling service from the FEI fueling station located in Langford, BC (Langford Fueling Station) (DanFoss-Langford Agreement), effective August 31, 2024 (Request);
B. By Order G-204-24 dated July 31, 2024, the BCUC approved the rates established in the DanFoss-Langford Agreement, effective August 1, 2024, on a permanent basis;
C. By email dated August 22, 2024, DanFoss provided written notice to FEI to cancel the DanFoss-Langford Agreement; and
D. The BCUC has reviewed the Request and determines that consenting to the rescindment of Tariff Supplement
J-36 is warranted.
NOW THEREFORE pursuant to section 61 of the UCA, the BCUC orders as follows:
1. Tariff Supplement J-36 is rescinded, effective August 31, 2024.
2. Tariff pages as filed in Appendix C of the Request are accepted as filed.
DATED at the City of Vancouver, in the Province of British Columbia, this 16th day of September 2024.
BY ORDER
Original signed by:
B. A. Magnan
Commissioner