ORDER NUMBER

G-267-25

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

River District Energy Limited Partnership

2026 to 2028 Revenue Requirements and Rates

 

BEFORE:

B. A. Magnan, Panel Chair

W. E. Royle, Commissioner

 

on November 13, 2025

 

ORDER

WHEREAS:

 

A.      On September 2, 2025, River District Energy Limited Partnership (RDELP) filed an application with the British Columbia Utilities Commission (BCUC) pursuant to sections 59 to 61 of the Utilities Commission Act, seeking approval of its revenue requirement and to increase both the capacity charge and the thermal energy charge by 10 percent each year for the calendar years 2026, 2027 and 2028 (Test Period), effective January 1 of each year, among other matters (Application);

B.      By Order G-229-25 dated September 19, 2025, the BCUC established the regulatory timetable for the review of the Application which included, among other things, intervener registration, one round of information requests (IRs), submission of letters of comment, and final and reply arguments;

C.      On October 28, 2025, RDELP filed its responses to IR No. 1;

D.      On October 29, 2025, RDELP filed a request to extend the deadline for filing its final argument from Friday, November 21 to Wednesday, November 26, 2025 (Extension Request) due to limited resources, and requested adjusting the subsequent stages of the regulatory timetable accordingly; and

E.       The BCUC has reviewed the evidentiary record, including the Extension Request, and considers that the following determinations are warranted.

 

NOW THEREFORE the BCUC orders as follows:

 

1.       The regulatory timetable is amended as set out in Appendix A to this order.

2.       The scope of IR No. 2 is limited to matters arising from RDELP’s responses to IR No. 1.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this      13th      day of November 2025.

 

BY ORDER

 

Electronically signed by Bernard Magnan

 

B. A. Magnan

Commissioner

 

 

Attachment


River District Energy Limited Partnership

2026 to 2028 Revenue Requirements and Rates

 

REGULATORY TIMETABLE

 

 

Action

Date (2025)

BCUC IR No. 2 to RDELP

Monday, November 24

Intervener IR No. 2 to RDELP

Thursday, November 27

RDELP responses to BCUC and Intervener IR No. 2

Thursday, December 4

RDELP final argument and reply to letters of comment

Thursday, December 18

Action

Date (2026)

Intervener final argument

Thursday, January 8

RDELP reply argument

Thursday, January 22

 